MINECO's timeline to resolve a 29-89 qualification
- Manual: opening a garment factory
- The 29-89 regime: benefits and qualification
- Audited
Statutory deadline: the Directorate issues its opinion "within a period of no more than thirty (30) days" from filing of the application (art. 21) and MINECO resolves "within a period of no more than fifteen (15) days" from that opinion (art. 22): 45 days in all, with the law not specifying whether they are business days (settled in the 2026-08-22 audit against SAT's consolidated text). In practice, the adviser consulted cites 30–45 business days "depending on the quality of the file". No fee or charge for the procedure was found.
The research is written in English; quoted figures, source names and the titles of legal instruments stay in the language their source published them in.
Figures
- Dictamen de la Dirección
- ≤30 días desde la solicitud
- Resolución del MINECO
- ≤15 días desde el dictamen
- Plazo práctico según asesor
- 30–45 días hábiles
Caveat
Sources
Related records
This layer is research: read from public sources by the archive's own team, every claim cited with the date it was consulted, and audited where it is marked so. It has not entered the verified store — no figure here was fetched back from its source or stamped with a retrieval time — so it wears no red provenance numeral and never mixes with the verified figures.