The eight steps to open an apparel factory

Dossier
Manual: opening a garment factory13-manual-fabrica.md
Domain
Opening a garment factorymanufactura-confeccion
Room
Invest · Opening a garment factory/invertir/manufactura-confeccion
Audited
Audited

The manual orders the process in eight steps: (1) choose municipality and model — own building, park lease, ZDEEP or free zone; (2) incorporate an S.A. and register it with the Mercantile Registry, the tax authority (SAT) and social security (IGSS) (advisers cite ~2–3 weeks for mercantile registration); (3) qualify under Decree 29-89 at the Ministry of the Economy (MINECO) — statutory ≤30 days for the opinion plus ≤15 days for the resolution (arts. 21-22), 30–45 business days per adviser; (4) environmental instrument at the Ministry of the Environment (MARN) per the listed-activities schedule of Governmental Accord 137-2016, license issued and delivered within ≤5 days of the approving resolution (art. 60); (5) power connection (EEGSA in the southern corridor) and water (well with municipal license plus MARN); (6) import machinery and inputs under temporary admission, with import duty (DAI) and VAT suspended for one year; (7) hire and run payroll at the CE1/CE2 maquila minimum plus employer charges; (8) export to the United States duty-free by meeting the CAFTA-DR yarn-forward rule. Timelines drawn from advisers or guides are not published law and remain to be verified in the data phase.

The research is written in English; quoted figures, source names and the titles of legal instruments stay in the language their source published them in.

Figures

Plazo legal calificación 29-89Portal SAT
≤30 días de dictamen + ≤15 días de resoluciónDec. 29-89 arts. 21-22, texto consolidado
Plazo de licencia ambiental tras resoluciónAG 137-2016 (copia OMC)
≤5 díasAG 137-2016 art. 60, texto 2016
Admisión temporal (suspensión DAI+IVA)Portal SAT
1 añoDec. 29-89 art. 12 vigente

Caveat

Adviser timelines (mercantile registration, 30–45 business days, 30 days for the power connection) are not published law

Sources

Related records

This layer is research: read from public sources by the archive's own team, every claim cited with the date it was consulted, and audited where it is marked so. It has not entered the verified store — no figure here was fetched back from its source or stamped with a retrieval time — so it wears no red provenance numeral and never mixes with the verified figures.