PEG-5 award outcome: projects, MW and price
- Energy, water and telecommunications
- The power market and its tariffs
- not audited
The CNEE approved without objection the award of 57 projects from 33 companies, contracting 1,258 MW of the ~1,400 MW required (90%). The dominant technology was solar paired with batteries (BESS), with 26 projects awarded; the reported price is ~US$101/MWh, more than 10% below the distributors' current purchase prices. Energia Estrategica headlines that 1,242 MW of solar with storage dominate PEG-5. These are all press figures (Prensa Libre, Energia Estrategica) still to be checked against the award record.
The research is written in English; quoted figures, source names and the titles of legal instruments stay in the language their source published them in.
Figures
- Proyectos / empresas adjudicadas
- 57 proyectos / 33 empresas
- MW contratados
- 1,258 MW de ~1,400 MW (90%)
- Proyectos solar + BESS adjudicados
- 26
- Precio reportado
- ~US$101/MWh (>10% bajo precios actuales de compra)
- Solar con almacenamiento (titular)
- 1,242 MW
Caveat
Sources
Organizations named in the answer
Related records
- Wholesale market participants, from generators to large users
- 2025 electricity generation mix and renewable share
- 2025 SNI production, consumption and average spot price
- Regulated EEGSA, DEOCSA and DEORSA tariffs and the social tariff
- Gran Usuario status and buying power outside the regulated tariff
- PEG-5 bids, MW submitted and process timeline
This layer is research: read from public sources by the archive's own team, every claim cited with the date it was consulted, and audited where it is marked so. It has not entered the verified store — no figure here was fetched back from its source or stamped with a retrieval time — so it wears no red provenance numeral and never mixes with the verified figures.